Let me summarise the actual Issue.
Issue : Sales Order Schedule Line showing future date for the Materials which are having Product Allocation even though the Stock is available and Allocation Qty also available in the PA Master Data we maintained..
We created one Sales Order for Line Item A and B. Line Item A is having Product Allocation. When we created Sales Order for both Line Item A and B we got Schedule Line Date as 13.06.2014. Then we Schedule the Re-Scheduling Job in V_V2 and check the effect. For Line Item A the Schedule Line Date got changed to 01.07.2014 and Line Item B it was same as before.
Would like to know is there any config setting at Schedule Line Level we have missed just want to cross check if there is any or something in Product Allocation Configuration.
Please refer screen shots below for more details of Sales Order before and after effect in Re-Scheduling.
Please provide your inputs on this.