Re: Planning Time Fence Value

$
0
0

Hi Mariano,

 

Thank you for the info. So in order to cater the emergency sales orders, we need to maintain the coverage profile for the FERT items.

 

Q1: To cater emergency sale orders, implementing planning time fence will not help?

 

Q2: Is the coverage profile to be maintained in material master?

 

Q3: Can you please explain the usage of coverage profile with some example?

 

Q4: Suppoe, i have maintained the planned delivery time as 5 days, GR processing time as 2 days & purchase processing time as 1 day in OMEW. So the "procurement lead time will be 5 + 2 + 1 = 8 days. What is the purpose of maintaining "purchase processing time in OMEW"?

 

Thanks