Is User Exit CONFPI03 or CONFPI04 will work? The requirement is

 

1) The quantity of Phase 20 which is confirmed, should be defaulted at phase 40 at the time of confirmation. I mean if Process Order quantity is 100 Units, and at phase 20, qty confirmed is 20 Units, then at the time of Confirmation, 20 Units, should appear . 1:1 Confirmation relationship between the phases.

2) And also Phase 40 confirmation should not be greater than Phase 20.

 

Badi workorder_confirm option is applicable only at while saving the Order.

 

Please suggest how to approach with Custom Logic

 