Hi cordero,
System never creates production orders..It creates planned orders after MRP run. You need to convert the planned orders to production orders...
Now if you want one production order per week you need to maintain the lot size as WB in material master in MRP 1 view as already suggested by Kiran...
So when you do MRP run system will generate one Planned order per week which can be converted to Production Order...
Thanks
Kumar