Re: Shift Plan issue:target plan is not complete for personnel number XXXX

$
0
0

HI,

 

This happens when Target plan is not complete.

Go to PP61, Target Plan and go to Change

Then on top there is a option in Shift Plan -Completeness and Save it.

Once saved then it will allow actual plan.

 

Regards,

Saureb